Final stage of ‘Aoka Mizu FPSO’ commissioning commences

Source: press release, 13 May 2019

‘Aoka Mizu FPSO’ (photo: Hurricane Energy/Ralph Ehoff)
‘Aoka Mizu FPSO’ (photo: Hurricane Energy/Ralph Ehoff)

UK-based Hurricane Energy plc has announced an operational update for the Early Production System development of the Lancaster field (Lancaster EPS).

On 11 May 2019 hydrocarbons were introduced into the Aoka Mizu FPSO’s process system. Introduction of hydrocarbons is the final stage of the FPSO’s commissioning and marks the commencement of the Lancaster EPS start-up phase.

During this phase, each of the two production wells will be individually tested and shut-in for data gathering purposes. Cleaning and testing (pigging) of the flowlines for flow assurance purposes will also take place during these shut-ins. The start-up phase will conclude with simultaneous flow from both wells for 72 consecutive hours, after which a further announcement of “First Oil” will be made.